Last updated: 11th June 2022

Last updated: 30th September 2021


Completed Project




LIST OF COMPLETED PROJECT UNDER P&D/QS CIRCLE, CAAB.

Sl No Name of the project Project Cost (Lac Tk) Actual Cost (Lac Tk) Comment
01. Construction of Cargo Apron in front of Cargo Terminal Building at  Shah Amanat International Airport, Chattogram. 7815.61 7686.03 Completed by June'2019
02. Link project for land acquisition for construction of Khanjahan Ali Airport under Public Private Partnership (PPP) 21748.83 18668.27 Completed by June'2019
03. Extension of Passenger Apron with other allied works at Saidpur Airport. 2309.25 2294.00 Completed by June'2019
04. Extension of Passenger Apron with other allied works at Jashore Airport. 2592.00 2562.57 Completed by June'2019
05. Extension of Passenger departure holding lounge at Osmani International Airport, Sylhet. 1155.00 1021.00 Completed by June'2020
06. Vertical extension of passenger departure holding lounge at Cox's Bazar Airport, Cox's Bazar. 750.00 680.00 Completed by Oct'2019
07. Consultancy Services for Development of Saidpur, Barishal & Osmani International Airport Projects (Design Phase),Sylhet 2760.01 2696.17 Completed by December'2019
08. Consultancy Services for Construction of Bangabandhu Sheikh Mujib International Airport. 13675.00 13686.00 Completed by June'2021

 

 

Last Updated on 23 July 2018